Agenda

IT Integration Standardization Phase

IT Integration Process Enablement Phase

Progress - Task Group

IT Integration Phases

IT Integration Punch List

Overall Progress

IT Integration Standardization Phase

AreaProgressIssuesMitigation
Phase 1 Transition 100%
HR/ERP consulting invoices undocumented -
IT Org./Dept. Transition 100%
Resource constraints and best practices lacking Acquirer support and control. Leverage Acquirer support tools
Acquirer Connectivity 75%
AD access to Acquirer assets. Resource mapping and PM required AD resource engaged
Acquirer Infrastructure 75%
Office move pushed to August. Network issues in Iowa Rolling schedule treated like standard site turn-up. Monitor TBM and upgraded circuit

IT Integration Process Enablement Phase

AreaProgressIssuesMitigation
Acquirer Connectivity - Continued75%
Carry over-Email cleanup, Carry over- AD coverageEmail complete by 6/20 AD kicked off 6/17
Acquirer Infrastructure - Continued75%
DR site shutdown, Carry over-final improvementsSite shutdown initiated Iowa scheduled
IT Team Development50%
Depth and strength to work with Acquirer IT. Availability to focus on business.Moved FTE to Chicago; engaged temp improvements. Reduce future risk
Acquirer Governance and Support10%
SharePoint team engaged. Apps not systematically governed yetSME assigned to critical apps Governance process ready to kickoff
Enablement - ERP25%
Kicked off 5/19Leverage PM best practices Coordinate dependencies Dedicated team and PM
Enablement - Bidding75%
Environment installed in local (NB) clusterOperations is integrated into the ERP program. In-house team has resources
Enablement - Job Controls10%
Awaiting ERP detail on open jobsLittle or no history will be leveraged
Enablement - Other10%
Other apps/processes did not surface with ownersOperations will own the gap and address as needed

Progress - Task Group

Task Group

  • Transition Carry-Over
  • NEWCO - I.T. Org & Dept Transition
  • Security & Access
  • Network Infrastructure
  • Enterprise Technology
  • Applications
  • Finance Enablement
  • Operations Enablement
  • HR Enablement

Open Items & Guidance

Transition Carry-Over: None

NEWCO - I.T. Org & Dept Transition: Define final scope for IT Standard, Move non-triage to Phase 2

Security & Access: WSU, Monitoring etc. at Sioux City, Business decision on WSU, Schedule monitoring solution

Network Infrastructure: Union Tower (WSU TBD), Set semi-monthly status

Enterprise Technology: Email - close out, AD - Plan, execute, mobility plan, Finalize outliers, incl WSU, Complete AD requirements for Acquirer, Support Acquirer mobility at Acquirer

Risk/Opportunity

NEWCO - I.T. Org & Dept Transition: OPP: Team development plan

Security & Access: RISK: Effective close out

Network Infrastructure: RISK: Effective close out

Enterprise Technology: RISK: Lack of focus; effective close out

Applications: OPP: Basic knowledge transfer, min. investment. RISK: Continued system failures

Finance Enablement: OPP: Budget capture; tight scope. RISK: Lack of end-to-end PM; full IT continuity

Operations Enablement: OPP: Budget capture; tight scope. RISK: Effective communications & change management

HR Enablement: OPP: Budget capture; tight scope. RISK: Visibility into scope/tasks