IT Integration Standardization Phase
IT Integration Process Enablement Phase
Progress - Task Group
IT Integration Phases
IT Integration Punch List
Overall Progress
IT Integration Phases
STANDARDIZATION PHASE (1 – 90 DAYS)
Coverage
Infrastructure Improvement Phase 1 competed, Phase 2 starting 3 offices Email Migration tested and piloted; staged pending business approval (bids)
Schedule
Email pushed to begin after May 30 due to heavy bid schedule
PROCESS ENABLEMENT PHASE (90 – 180 DAYS)
Coverage
ERP Migration kicked off; planning session with all players in Arkansas
Bid users identified with business analysis underway
Schedule
ERP Planning May 15 – 16; Go live October 1 ...